A 55-kilometre line between Dakar and the airport
The new section of about 19 kilometres brings the total length of the TER to 55 kilometres between Dakar and AIBD. It extends the 36-kilometre stretch between Dakar and Diamniadio that opened in December 2021. The cost announced at the inauguration for this second phase is over 300 billion CFA francs.
The full journey takes about 55 minutes. The time stays the same at rush hour, which finally makes it possible to plan your departure for a flight without allowing a huge margin for the motorway. Passengers no longer have to change vehicles at Diamniadio: the train takes them all the way to the terminal.
A train every 24 minutes to the airport
The opening came with a new timetable and seven new trains. A train now runs every 8 minutes between Dakar and Diamniadio, compared with 10 minutes before, and every 24 minutes between Diamniadio and AIBD. Some trains therefore terminate at Diamniadio, and the platform screen shows the destination of each train.
The network reaches the airport with solid experience behind it: it has passed the mark of 100 million passengers since it opened. Before this extension, it carried up to 90,000 passengers a day.
Two free weeks, then fares based on your station
To introduce the line, the Diamniadio–AIBD section was first offered free of charge. This free period, planned until 4 October, was extended to Sunday 11 October inclusive. Since Monday 12 October, the fare table published by SENTER and SETER sets prices according to the departure station and the class chosen.
The fare on the original section does not change for journeys within it: Dakar–Diamniadio stays at 1,500 CFA francs (€2.29, about $2.65).
A first big test with the Youth Olympic Games
The line opened at a strategic moment. Diamniadio is home to some of the Games venues, including Dakar Arena, Dakar Expo Center and the Abdoulaye Wade Stadium. Until 13 November, shuttles link Diamniadio station with the competition sites. For delegations and spectators arriving by plane, the train now offers a direct link between the airport and the heart of the Games.
Sébikotane, Thiès, Mbour: the next stops
The line keeps growing. The foundation stone of Sébikotane station was laid on 20 June 2026, and a temporary service lets residents reach the network until it opens.
Further on, phase 3 aims to extend the TER to Thiès, over about 25 kilometres. The memorandum signed on 24 July 2026 commits 10 million euros to preliminary design studies, or about 6.5 billion CFA francs. An extension to Mbour is also under study.
Along the line
Diamniadio, 19 kilometres from the airport by rail, is home to the new town, its ministry buildings known as the "spheres" and its major sports venues. From the airport, Saly and Somone are reached by road. At the Dakar end, the terminus leaves you a short walk from the Plateau, the port and the Museum of Black Civilisations, which stands opposite the Grand Théâtre national. From 19 November, central Dakar also hosts the 16th Biennale of Contemporary African Art, until 19 December.
Practical tips
From Dakar or a zone 1 station, a ticket costs 4,000 CFA francs in second class (€6.10, about $7.07). It costs 3,500 CFA francs (€5.34, about $6.19) from Yeumbeul or a zone 2 station, and 3,000 CFA francs (€4.57, about $5.31) from Diamniadio. First class costs 10,000 CFA francs, whatever the departure station (€15.24, about $17.68).
These prices are for a single journey. Regular travellers between Dakar and the airport can buy a book of ten journeys for 35,000 CFA francs in second class and 70,000 CFA francs in first class, that is €53.36 (about $61.89) and €106.71 (about $123.79) respectively. Tickets are sold at TER ticket offices and sales points, and the Sama TER card can be topped up with tickets.
If your flight lands late, plan a taxi or a private transfer, as trains stop running at 10 pm, while many flights arrive between 10 pm and 3 am. For a daytime departure, allow an hour on the train, then add the usual check-in time. Each passenger is allowed two suitcases and a handbag. Up-to-date timetables are on terdakar.sn.
5:19 pm, the power finally comes on
On Saturday 13 December 2025, regular TER passengers find the platforms empty. No trains run all weekend, to make way for the extension works to the airport. The technical teams have two days for an operation that daily service does not allow.
On the Sunday, late in the day, the long-awaited moment arrives. On 14 December 2025 at 5:19 pm, the overhead line is energised, making full electrification of the line to the airport possible.
The engineers know what comes next. For the first phase, energising the line on 3 August 2021 came before commercial service on 27 December of the same year, a little under five months later. For the airport, it will take more than nine months of trials and approvals before the first commercial train pulls into the station, on 28 September 2026.